Construction of second part of new integrated terminal at Chennai airport further delayed to June 2026

Around 25% of construction work has only been completed till now in the second part of the terminal building; excavation and building the basement with hard rock like conditions make it challenging for the contractor to expedite work

Construction of second part of new integrated terminal at Chennai airport further delayed to June 2026
Around 25% of construction work has only been completed till now in the second part of the terminal building; excavation and building the basement with hard rock like conditions make it challenging for the contractor to expedite work